凯旋会展新城21年9月**新工程进度
2021-08-31 11:16![](https://mimages.jiwu.com/images/v7.0/jlq2.png)
南充买房交流群-68群(400)
加入群聊
![图片](https://img4-build.jiwu.com/album/auto/2020/08/06/160353610491.jpg/710x400)
![图片](https://img6-build.jiwu.com/album/auto/2021/03/16/03381957825.jpg/710x400)
![图片](https://img9-build.jiwu.com/album/auto/2020/11/26/040117959386.jpg/710x400)
![图片](https://img9-build.jiwu.com/album/manual/2021/11/29/104705861230.jpg/710x400)
![图片](https://img5-build.jiwu.com/album/manual/2019/11/16/145416684423.jpg/710x400)
![图片](https://img5-build.jiwu.com/album/auto/2021/03/16/204706425348.jpg/710x400)
![图片](https://img5-build.jiwu.com/album/auto/2020/10/19/184326806995.jpg/710x400)
![图片](https://img4-build.jiwu.com/album/auto/2020/11/16/064347931436.jpg/710x400)
![图片](https://img6-build.jiwu.com/album/manual/2021/10/06/101016012475.jpg/710x400)
![图片](https://img4-build.jiwu.com/album/auto/2021/03/16/033819354460.jpg/710x400)
![图片](https://img10-build.jiwu.com/album/auto/2021/03/16/20470699450.jpg/710x400)
![图片](https://img1-build.jiwu.com/album/auto/2021/04/27/063927748891.jpg/710x400)
19号楼主体施工至15层;
20号楼主体施工至27层;
21号楼主体施工至28层;
22号楼正在进行施工电梯处外墙清洗;
23号楼正在进行施工电梯处外墙抹灰,铺贴外墙砖;24、25号楼主体施工完成;
26号楼外墙施工完成80%,内墙抹灰完成至17层;
36号楼主体施工完成至31楼,砖砌体砌筑至12层;
37号楼主体施工完成至16楼;
38号楼2单元主体施工完成至3楼,1单元施工完成至负1层顶板;
39号楼32层二次结构,各楼层后塞口砌砖,清理楼面。
过往动态
-
在售 2021-08-24凯旋会展新城樱花观景大道
-
活动 2021-08-12凯旋会展新城七夕优享总价54.5万元起
-
特价 2021-07-21凯旋会展新城南充吉屋网专享一口价房源 享私岛江景华宅
买房交流群
3190
人正在讨论南充楼市
![](https://mimages.jiwu.com/images/v7.0/jlq2.png)
南充买房交流群-68群(400)
所属楼盘